Questions from bidders

1. Can the Appendices be provided in Word Format?

            Answer: Yes, please see procurement tab on the website.

2.  Can an estimate of Marshalltown Operational costs be provided?

            Answer: Yes, please see Operational Costs on the procurement tab on the website.

3.  Is the deadline date via the cover page or the timeline on page 32 of the RFP?

            Answer: The deadline is November 13, 2020

4.  In the budget, is “Profit Cost” the same as indirect costs?

Answer: Profit and indirect costs are separate categories.  If you are proposing an indirect rate your Negotiated Indirect Cost Agreement (NICA) will be requested during contract negotiations.   Profit guidelines for different entities are outlined in the Code of Federal Regulations (CFR).